ROMANIA · SOLAR LAND ORIGINATION
Land that can actually support the investment.
A solar project begins before permitting and before grid execution. It begins with land that can be controlled, documented and developed.
Tudor Business Investments originates and structures land positions for utility-scale solar projects in Romania, coordinating landowner engagement, site control, cadastral work and the local execution required to move from an identified site to an investor-ready land package.
Land is not simply an input into a solar project. It is the foundation on which every later development decision depends.
01 · The Land First
A viable project starts with a viable site.
Not every large agricultural parcel is a development site. Before an investor commits capital, the land position must be tested against ownership, cadastral structure, physical access, development constraints and realistic grid relevance.
- Ownership & title — ownership, succession history, encumbrances and competing rights.
- Parcel structure — geometry, fragmentation, cadastral accuracy and consolidation requirements.
- Physical access — public-road access, technical-road corridors and rights of way.
- Development constraints — agricultural classification, protected areas, utilities, water, archaeology and other location-specific restrictions.
- Grid relevance — the site must be assessed together with a credible route to network access, not in isolation.
LAND AREA → CONTROLLED AREA → DEVELOPABLE AREA → INVESTOR-READY SITE
02 · Land Screening
Screening before negotiation.
TBI begins with the investor mandate and works backwards from the project requirements. A typical screening process considers target MW and indicative land requirement, parcel continuity, ownership concentration, cadastral status, access, existing infrastructure corridors, agricultural classification, environmental constraints and indicative proximity to relevant electrical infrastructure.
The objective is not to secure the greatest number of hectares. It is to control the hectares that matter.
03 · Legal & Cadastral Due Diligence
Site control is only as strong as the underlying title.
Before a land position becomes investment-grade, the legal and cadastral chain must be understood. The workstream may include title review, land-book history, encumbrances, surface discrepancies, parcel boundaries, overlaps, access rights, easements and a traceable landowner register showing parcel and negotiation status.
Role clarity. TBI coordinates the local land workstream. Formal legal opinions and specialist legal due diligence remain within the mandate of the appointed lawyers.
04 · Site Control & Superficies
Control before commitment.
For utility-scale development, land control must protect both the development phase and the eventual financing or transfer of the project. Depending on the structure, this may involve a promise or preliminary agreement, a right of superficies, selective acquisition and ancillary rights for roads, cables, substations and temporary construction areas.
- Promise / preliminary agreement — secures the development window before the definitive right is constituted.
- Superficies — provides a real right allowing project infrastructure to be built and maintained on land owned by another party.
- Ownership / acquisition — used where acquisition is commercially and strategically justified.
- Ancillary rights — access roads, cable corridors, easements, substation areas and temporary construction rights.
The contractual architecture should anticipate assignment, financing, project transfer and successor rights, rather than treating the original developer as the only possible project holder.
05 · Cadastral Execution
The cadastral structure must follow the project.
A land agreement does not replace a workable cadastral configuration. Where required, TBI coordinates the route from the existing parcel structure to a project-specific configuration that can identify the PV field, substation or BESS area, technical roads, cable corridors, temporary construction areas and land remaining outside the project footprint.
EXISTING PARCEL → PROJECT PERIMETER → REQUIRED SUBDIVISIONS → ACCESS & INFRASTRUCTURE CORRIDORS
06 · Agricultural & Planning Framework
Land strategy must reflect the regulatory route.
Romania’s current land framework permits certain renewable-energy investment objectives on specified agricultural land in extravilan, subject to the conditions of Law 18/1991, Article 92, as amended, and to the applicable construction and agricultural-circuit approvals. Eligibility must therefore be tested parcel by parcel, taking into account land class, category of use, project configuration and the legislation in force at the date of the investment decision.
REGULATORY NOTE · 2026
Land eligibility, agricultural-circuit treatment and permitting requirements should be confirmed for the specific site and against the legislation in force when the project proceeds.
07 · Grid Readiness Starts With Land
Grid strategy is now an upstream land question.
From 1 January 2026, the capacity-allocation methodology introduced by ANRE Order 53/2024 applies, in the circumstances set out by the regulation, to production and production-consumption sites with installed generation capacity of at least 5 MW that do not hold a valid technical connection approval at the date the methodology applies.
This makes grid relevance an upstream land-screening issue. A high-voltage line visible near a property is not, by itself, evidence of available network capacity or a viable connection route.
LAND → GRID CONTEXT → PROJECT FIT
08 · Investor-Ready Land Package
From individual parcels to one controlled development position.
An investor-ready land package should provide clarity on what is controlled, by whom, for how long, under what legal instrument, with what access and cadastral structure, and for what development purpose.
INVESTOR MANDATE → LAND SCREENING → OWNER MAPPING → LEGAL DD → SITE CONTROL → SUPERFICIES / RIGHTS → CADASTRAL EXECUTION → ACCESS & EASEMENTS → GRID READINESS → INVESTOR-READY LAND PACKAGE
That is the point at which land becomes a development asset rather than simply a collection of parcels.
SOLAR LAND ORIGINATION · ROMANIA
Define the mandate before we define the site.
TBI works with developers, strategic operators and investment capital seeking controlled access to solar development opportunities in Romania.
Confidential Investor Briefing →
contact@investmentsinromania.eu
TBI · SOLAR PLATFORM